Arbitration tribunal finds VGCP breached obligation to announce commercial operation date
A majority of the arbitration panel ruled that a VGCP subsidiary breached its duty to timely announce the commercial operation date (COD) for the Calcasieu project. VGCP says the breach does not alter the SPA terms, noting twenty cargos have been delivered, and the final award will be capped at $170 million.
Key points
- The arbitration panel, by majority, found that VGCP's subsidiary breached its duty to promptly announce the commercial operation date (COD) for the Calcasieu project.
- The ruling is a majority arbitration award, with one arbitrator dissenting.
- Under the award, the final judgment will be subject to the seller's aggregate liability cap of $170 million set out in the SPA.
What happened
The arbitration panel, by majority, found that VGCP's subsidiary breached its duty to promptly announce the commercial operation date (COD) for the Calcasieu project.
Case status
The ruling is a majority arbitration award, with one arbitrator dissenting.
Potential consequences
Under the award, the final judgment will be subject to the seller's aggregate liability cap of $170 million set out in the SPA.
Original sources
Cite this article
The fingerprint identifies the exact version of each original that the article was written from; the original stays at its source.
Follow Venture Global
A notification in your browser or on your phone when we publish about Venture Global. Free, no email, no account, no app.
Prepared by AI from official company documents; automatic checks and an AI editor review it before publication, and not every article is read by a person. This is not investment advice. Editorial standards