Kinross Gold reports $583.2 million profit and safety incident at Bald Mountain

Kinross Gold reported $583.2 million in net earnings for the third quarter of 2026 and confirmed over $950 million in capital returned to shareholders year-to-date. Separately, two partner employees died following separate September incidents at the Bald Mountain site.

Verified against 4 archived primary sources · SHA-256 recorded Inspect sources & citations ↓
a large truck driving down a dirt road
Photo by MiningWatch Portugal on Unsplash
$583.2 million
Quarterly net earnings
$950 million
Capital returned YTD

Key points

  • Third-quarter net earnings were $583.2 million, or $0.49 per share, with $591.3 million in adjusted net earnings.
  • Third-quarter gold production was 424,693 gold equivalent ounces, with 410,245 ounces sold.

Financial results and shareholder returns

Third-quarter net earnings were $583.2 million, or $0.49 per share, with $591.3 million in adjusted net earnings. Performance was supported by an average realized gold price of $4,249 per ounce, up 23% year-over-year. As of September 30, the company held $4.4 billion in total liquidity, including $2.6 billion in cash and $1.7 billion in available credit, with no debt maturities until 2033.

The company has returned over $950 million to shareholders year-to-date through dividends and share buybacks. Kinross increased its capital return target to 50% of free cash flow. A dividend of $0.04 per share is payable on December 3, 2026, to shareholders of record on November 19.

Operations and safety

Third-quarter gold production was 424,693 gold equivalent ounces, with 410,245 ounces sold. These figures are lower than in the same period of 2025 due to planned production decreases at Fort Knox and Bald Mountain.

Two separate incidents in September 2026 at the Bald Mountain site resulted in the deaths of two contractor employees. Kinross did not disclose the potential impact on future operating costs or regulatory risks.

First gold was poured at the Redbird 1 deposit (Bald Mountain) in early October, and Redbird 2 pits are fully permitted. At the Great Bear project, surface construction is nearly complete, and detailed engineering is over 55% finished.

Items to watch

Shareholders should note the December 3, 2026, dividend payment date, which confirms the current capital return policy.

Monitor company updates regarding the operational impact and any regulatory reviews stemming from the Bald Mountain incidents.

Original sources

  1. 6-K filing, October 28, 2026October 28, 2026SHA-256 of our archived copy 1689918ceec2…
  2. 6-K EX-99.1 filing, October 28, 2026October 28, 2026SHA-256 of our archived copy 3afdecf6e8d6…
  3. 6-K EX-99.1 filing, October 28, 2026October 28, 2026SHA-256 of our archived copy dc5ba0bc5656…
  4. 6-K EX-99.1 filing, September 24, 2026September 24, 2026SHA-256 of our archived copy 9300f15921af…
Cite this article

The fingerprint identifies the exact version of each original that the article was written from; the original stays at its source.

Prepared by AI from official company documents; automatic checks and an AI editor review it before publication, and not every article is read by a person. This is not investment advice. Editorial standards